Scheduled Date and Time:

Start - December 4th, 2015 @ 8:00PM EST
End - December 5th, 2015 @ 12:00AM EST

Maintenance Window:
4 Hours

Datacenter Location:
Orlando.DC2

Maintenance Type:
In order to ensure the most secure and reliable services possible, we will be updating firmware on the switch your server is connected to. To complete this process, we will need to power cycle the switch. This will cause a brief period of service unavailability for all servers using this switch.

Estimated Downtime:
We understand the importance of minimizing downtime while performing maintenance and for this reason we will do everything we can in hopes that we can expedite the process. As it stands we expect no more than 20 minutes of downtime during the maintenance window as the switch is updated and power cycled. Should there be any complications, we will have personnel on-site to address these issues immediately.

We do apologize for any inconvenience and ask that you please plan accordingly.

Thursday, December 3, 2015